INFRASTRUCTURE DESIGN AND PROJECT EXECUTION

 

 

 

 Design and construct the Infrasound station IS01 Pilcaniyeu, Argentina composed by 8 elements and a CRF, from the scratch to the operation (certified in Dec/2019);

 

✔ Security improvements to the equipment vault with entrance in two levels, first one at the level of the tamper switch, giving time for the security staff to reach the remote element before the burglar manages to break through the second level. All designed and implemented in stainless steel material. After this implementation (2018) the station IS09 did not suffer any recurrence of battery robbery.

 

✔ Design and manufacture customized equipment support in stainless steel.

 

Installation of raised floor and structured cabling trays at the CRFs of the stations IS01 and IS09/PS07;

Pressure tests of the pipe arrays for leaks and parts replacement to guarantee the WNRS efficiency.